Fort Saskatchewan Path2Zero Expansion Connection

June 11, 2025
Dow Chemical Canada ULC (Dow Chemical) has applied to the AESO for transmission system access to reliably connect its proposed Fort Saskatchewan Path2Zero Expansion (Facility) in the Fort Saskatchewan area. Dow Chemical’s request can be met by the following solution:
- Add two 240 kilovolt (kV) transmission lines to connect the Facility to the existing Lamoureux 71S substation in a radial configuration.
- Modify the Lamoureux 71S substation, including adding four 240 kV circuit breakers.
- Add or modify associated equipment as required for the above transmission developments.
THE AESO
- Must plan the transmission system and enable access to it for generators and other
qualified customers. - Can approve eligible projects through the ANAP Rule and for non-eligible projects, the
AESO will prepare and submit a NID to the AUC for approval.
ALTALINK
- Is the transmission facility owner in Fort Saskatchewan area.
- Is responsible for detailed siting and routing, constructing, operating, and maintaining
the transmission facilities. - Is regulated by the AUC and must apply to the AUC for approval of its transmission
facilities applications.